The first step is to
install the sill plates on the foundation wall . This gives you a place to
nail 2x4 bracing to hold columns and beams in place while you install
them. Once set in place these braces hold the steel till the floor joists
are nailed in to take their place.
|
|
Before I continue, a word of caution. Homebuilding can be a dangerous
activity. Care and safety are a must in all phases of the construction
process. Setting steel definitely falls into this category. Beams can
weigh anywhere from 100 to 400 pounds depending on their size and length.
Beams can be lifted into place manually but I would recommend the use of a
crane. Not only can the beams be put in place safely, but it can also
quicken the process. |
With the sill plates in place the steel can be set. One end of the
first beam typically starts in a beam pocket formed into the top of the
foundation wall. The other end sits on top of a lally column. A typical
column is 3 1/2" in diameter and filled with concrete. It has a flange
welded to the top with holes in it that match holes in the bottom flange
of the beam. The beam is lowered onto the column and then bolted together.
To make this happen, I like to use four people. One to hold the beam in
the pocket, one to hold the column, one man on a ladder to guide and bolt
the beam onto the column and one man to nail off bracing to sill plates.
Braces (2x4's) are laid flat on the bottom flange of the beam on both
sides of the web and then nailed to the sill plates on opposing walls.
|
Find a Qualified Home Building Contractor in Your Area |
|
Get Free Quotes. Easy, Quick and No
Obligations!
For the home improvement or home remodeling project that is
too big for you, check out our partner
NeedContractor. They are a national
resource for finding pre-screened, insured, and licensed home improvement
and remodeling contractors in your local area.
|

|
|
Get Matched in 48 hours with Home Building Contractors! |
The next beam is now ready to be set. With one person holding the next
column, the next beam is lowered onto the new column and the previous
column. Men on ladders guide it into place and bolt it down. Again 2x4's
are used to brace the beam to the outside foundation walls. This procedure
is repeated until you get to a beam pocket at the other end of the
building, or a column that terminates at an opening.
To keep beams level and straight, I like to use a dry line from beam
pocket to beam pocket (this can also be done with a laser). First I drive
a nail in the sill plate corresponding with the edge of the beam. Most
beams run pocket to pocket. If this is the case I'll drive a nail in the
plate by that pocket at the same dimension as the first nail, measured
from a common reference point, usually the front or back sill plate. I now
have a reference point to line up the edge of the beams with and result in
a straight installation.
Assuming the foundation and sill plates are level, this string can be
used to level the steel beams (again, a laser can be used). After most
beam installations a 2x plate is either bolted or shot with a powder
actuated tool to the top of the beam. This is to bring it level with the
sill plates and to provide nailing for the floor joists. Using a 2x block
as a gauge, lay it on the top of the beam where it sits on a column. This
simulates the plate that will be installed later. Shim the column till the
block touches the bottom of the dry line. Repeat this for every column.
Columns are shimmed with steel plates of various thicknesses. These shims
are provided by the steel supplier.
The next step is to plumb the lally columns on their concrete pads.
Using a 4-foot level, the columns are tapped into plumb with a sledge
hammer. Make sure the steel shims remain under the columns. After all
columns are plumbed up, the concrete floor can be poured. This holds the
columns in place.
The next step is to frame the floor. Once the floor joists are nailed
in place all bracing can be removed. The joists are now holding the steel
in place.
Just like the foundation, setting the steel straight and level is
important to producing a quality home.
(c) Mike Merisko
www.sawkerfs.com
About the Author: Mike Merisko has been a carpenter for 26 years. Most
of those years were spent in the homebuilding and remodeling industries. He was
also in business as a carpentry and general contractor. While that is his forte,
he also has experience in bridge building, commercial construction, and exhibit
building which is how he earns his living these days. You can browse through
articles by him and others at his website
http://www.sawkerfs.com or visit his blog at
http://www.sawkerfs.blogspot.com
Other Related Articles